Madrid schools project
Normetal is one of a number of companies that were engaged by the Community of Madrid in September 2020 to expand classrooms, in the context of the COVID-19 health crisis. The project includes expansions at 5 schools, totalling 2,400 m2, while complying with the technical building code and providing finishes tailored to each case and each specific setting.
The customer’s entire original project was adapted to the modular construction system, thereby guaranteeing urgent completion. The first unit was delivered within a period of 10 days after the award. The following units were delivered with deadlines of 8 weeks each.
The project took place at the following schools: Héroes de 2 de mayo Elementary School, Antonio Fraguas “Forges” Secondary School, Jane Goodall Secondary School, Tempranales Elementary School and Santo Domingo Elementary School.